Drywall contracts decide when a sub gets paid as much as what it builds: whether payment waits on the general contractor’s own check, how much may be held back as retainage, and what notice must come with any withholding. This is general education, not legal or tax advice; confirm specifics with your own attorney or CPA.
Read the payment article before the scope and the schedule
The payment article is where a subcontract says when money moves, what can be held back and what notice is owed, so read it before the scope, the schedule or the insurance exhibit.
Some general contractors write their own subcontract; others start from the standard contractor–subcontractor agreement form many projects use and add riders. Either way, the terms that decide your cash sit in connected places: the payment article, the retainage clause, the withholding or back-charge language, the change-order procedure and the dispute section. Read them together, because each can change how the others work.
The insurance requirements usually sit in a separate exhibit, and the commercial drywall contractor insurance page covers it under its heading on what the subcontract asks your policies to promise. This post stays on the money. Getting onto a general contractor’s bid list is the subject of the post on commercial drywall subcontractors and bid lists.
The federal construction payment rules in the Federal Acquisition Regulation are quoted below because they spell out what many private subcontracts leave to negotiation. They are the federal-contract example, not the rule for a private job, where the subcontract and the law of the state where the job sits decide.
How a progress payment travels up the chain and back down
On a commercial job, your pay request usually rides inside the general contractor’s own request to the owner, so a late or incomplete request on your side can slow the whole draw. The general contractor gathers each trade’s billing, sends the package up, and pays the trades after the owner pays it.
The federal clause on payments under fixed-price construction contracts shows how closely the pieces are tied. The prime contractor’s request includes “A listing of the amount included for work performed by each subcontractor under the contract.” It also certifies that subcontractors have been paid from earlier draws and will be paid from the current draw “in accordance with subcontract agreements”. The clause adds that “This certification is not to be construed as final acceptance of a subcontractor’s performance.” Being paid on a draw does not mean the general contractor has accepted your finish.
On private work, the subcontract sets the billing schedule, the form of the pay request and the backup it needs, such as a schedule of values or lien waivers. Send what it asks for, on time, in the format it names.
Pay-when-paid: your check waits on the general contractor’s
A pay-when-paid term ties the timing of your payment to the general contractor’s receipt of its own payment from the owner. It is common in commercial subcontracts.
Federal construction writes this link into the rules. The federal payment clause for construction subcontracts requires the prime contractor to put into each subcontract “A payment clause that obligates the Contractor to pay the subcontractor for satisfactory performance under its subcontract” within a set period counted “from receipt of payment out of such amounts as are paid to the Contractor under this contract.” It also requires an interest penalty clause for late payments, and the prime must “Require each of its subcontractors to include such clauses in their subcontracts with each lower-tier subcontractor or supplier.” A drywall sub working under another sub on a federal job is meant to get the same terms.
The government holds itself to a similar rule. The Bureau of the Fiscal Service’s prompt payment page says “Congress passed the Prompt Payment Act to require Federal agencies to pay their bills on a timely basis; to pay interest penalties when payments are made late, and to take discounts.”
Private subcontracts are not bound by these federal clauses. States set their own prompt-payment rules, and they differ, so the federal clause is a model of what to look for rather than a promise about your job.
Pay-if-paid is a different promise
Pay-if-paid makes the general contractor’s receipt of payment a condition of your payment, not just a matter of timing. The words look almost the same, but the risk they shift differs.
In plain words, a pay-when-paid clause is usually read as saying when you will be paid: you wait for the owner’s payment, but the money is still owed if that payment is slow. A pay-if-paid clause is usually read as saying whether you will be paid: if the owner never pays, the general contractor may argue it never owes you.
Which reading a clause gets turns on its exact wording and on the law where the job sits. Some states will not enforce a true pay-if-paid condition, and others enforce it only when the wording is clear. The rules vary by state, and the state pages are the place to start before an attorney reads the clause against your state’s law.
Look for phrases that make payment to the general contractor a condition precedent to your payment, or that say the sub assumes the risk of the owner’s nonpayment. Those are the words to bring to your attorney before you sign, not after the owner stops paying.
Retainage: the share held back until the job is done
Retainage is a portion of each progress payment held back until the work, or the whole project, is finished. It protects the payer against unfinished or defective work, and it means part of every draw reaches the sub much later.
The FAR’s policy on progress payments under construction contracts is plain about its limits: “Retainage should not be used as a substitute for good contract management, and the contracting officer should not withhold funds without cause.” It also says “Upon completion of all contract requirements, retained amounts shall be paid promptly.”
Between the prime and its subs, the federal payment clause leaves the amount to the parties, allowing retention of “a specified percentage of each progress payment” on terms the subcontract sets, with recognition of a sub’s ability to furnish bonds.
On a private job, read the retainage clause for how much is held, what event releases it, and whether release of your share waits for the whole project or only for your own scope. Why that gap strains a crew’s cash is covered in the financing post’s section on why a busy crew still runs short, and recording retainage in the books belongs to the post on accounting for drywall contractors.
Public work can add another layer. As an example from a single state, the Washington State Department of Revenue’s public works Q&A for contractors answers the question “Now that my job is done, how do I get my retainage from the project?” The public agency holds the retainage and “must wait for releases from the Department of Revenue, the Employment Security Department and the Department of Labor & Industries (affidavit of wages paid) before they can release retainage.” That describes Washington’s public works only; the Washington state page covers the rest of that state’s picture, and other states set their own rules.
Withholding and back-charges: get the reasons in writing
When a general contractor holds back more than the agreed retainage, the subcontract should require it to tell you in writing how much, why, and what will release it. If yours does not, ask anyway.
The federal payment clause is a clean model. It lets a contractor withhold under the subcontract, but says “The Contractor shall issue a written notice of any withholding to a subcontractor (with a copy furnished to the Contracting Officer), specifying” what follows: “The amount to be withheld;” then “The specific causes for the withholding under the terms of the subcontract; and” finally “The remedial actions to be taken by the subcontractor in order to receive payment of the amounts withheld.” After the problem is fixed, the contractor is to pay “as soon as practicable after the correction of the identified subcontract performance deficiency”.
A back-charge works much the same way: the general contractor deducts the cost of something it says your crew caused or failed to do. The contract decides whether the deduction is allowed and what notice must come with it. Whether insurance has any role is a separate question, and the commercial drywall page’s FAQ on back-charges takes it up; this post does not.
Real-World Scenario: A drywall sub finished a commercial tenant space, billed on time, and received a draw well short of the billing, with no explanation. The sub’s owner asked the general contractor’s project manager, in writing, for the amount withheld, the reason under the subcontract and what would release it. The reply named a damaged corner bead run and an unfinished closet. The crew fixed the bead and the closet, sent photos with the next pay request, and the withheld amount came back with that draw instead of turning into a dispute.
Change orders: written down before the extra board goes up
Extra work should be in a signed change order before the crew does it, because a verbal request from the field is the hardest thing to get paid for later. Added soffits, a higher finish level asked for at the wall, or re-hanging after another trade moves a line are common examples.
The federal changes clause for construction shows the discipline. Changes are made “by written order designated or indicated to be a change order”. A direction that is not labeled a change counts only if the contractor gives written notice stating “The date, circumstances, and source of the order” and “That the Contractor regards the order as a change order.” The price adjustment is written down too: the contracting officer “shall make an equitable adjustment and modify the contract in writing.” And timing matters: “No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract.”
Your subcontract will name who can approve a change, how fast you must give notice, and what happens if you do the work without a signed order. Change orders can also matter outside the contract, since some states count them toward a contractor’s license threshold; the state pages cover that rule where it applies. Writing a bid so that the scope is clear from the start is the subject of the post on how to bid drywall jobs.
When payment stalls: disputes, bonds and lien rights
If a general contractor will not pay, your options come from the subcontract, any payment bond on the project and the lien law of the state where the job sits. Start with the dispute section, which may require notice or a particular forum.
On federal work, the payment clause keeps the government out of the middle: a payment dispute between the prime and a sub “does not constitute a dispute to which the Government is a party.” The clause also leaves the parties’ other contractual, administrative and judicial remedies in place.
Bonded projects add a payment bond. What that bond is and who it answers to are explained in the licensed, bonded and insured post and in the financing post’s section on bonded commercial work, so this post does not repeat them.
Lien rights are state law. A mechanic’s lien can let an unpaid contractor make a claim against the property it improved, but whether a drywall sub has that right, what preliminary notice must come beforehand, and how long the right lasts all vary by state. Lien waivers are often traded with each payment; a conditional waiver usually takes effect only when the payment clears, while an unconditional waiver usually takes effect when signed. Ask your attorney before you sign either kind, and check the state pages for where you work.
A read-through list before you sign
Read the subcontract for the terms that decide when you are paid, and mark anything unclear for your attorney while it can still be negotiated.
- The payment trigger. Does the wording read as timing (pay-when-paid) or as a condition (pay-if-paid)?
- Retainage. How much is held, what releases it, and does release wait for the whole project?
- Withholding and back-charges. Does the general contractor owe you written notice of the amount, the cause and the fix?
- Change orders. Who can approve a change, and what notice must you give before extra work?
- Pay requests. What backup, forms and lien waivers must go with each request?
- Disputes. What steps come before a claim, and where is it heard?
Then read the insurance exhibit with your agent; the general liability page and the drywall contractor insurance hub are the places to start, and homeowner-paid repair work has its own notes on the residential drywall page. When the subcontract is ready, request a quote.